- Period:
- 40 weeks
Scope of works:
Our performance and success on an adjoining project, which was delivered ahead of programme, impressed and allowed.
OCS to successfully secure this 12 Story RC Frame in Ealing.
OCS utilised our own in-house equipment for the works. Peri Trio Formwork was used for casting of vertical elements. The first Floor transfer slab was 950mm deep and was supported using OCS owned Peri GT 24 Girders with a head room in excess of 6 metres.