- Period:
- 60 weeks (Completed 4 Weeks Early)
Scope of works:
OCS were appointed to construct a 23 Story RC Frame in Bracknell. The scope of works consisted of OCS providing Craneage, Formwork & Falsework equipment along with Falsework Designs.
Formwork & Concrete Logistics
OCS utilised our own in-house equipment for the works. Peri Trio Formwork was used for casting of vertical elements. OCS provided a static pump and placing boom to place concrete on the upper levels of the building for slab pours with the Tower Crane Supplementing vertical concrete elements