Southall Station Platform 3 Widening


Rail


Client:
VINCI
Period:
10 Days (228hr) Christmas Possession

Scope of works:
Oliver Connell carried out the Widening of Platform 3 at Southall Station for VINCI Taylor Woodrow on the Crossrail West project. The work consisted of the breakout of the existing platform, construct new platform with pre-cast Z-Units, install new 9 way multiduct, drainage, coper and tactile and resurface the new platform. The work was carried out on a 228hr Christmas Possession. Oliver Connell completed the works and handed back the new platform 2 days (48hrs) ahead of schedule.

 